Under this Task Order, Pond Constructors performed various repairs and upgrades to petroleum tank systems at fifteen locations throughout the continental United States (CONUS). The work was performed under the direction of DLA-Energy’s Centrally Managed Program with input from the DLA SRM Group. The initial statement of work included base repairs and upgrades to each tank to comply with current UFC 3-460-01 and AST Standards where they applied. As each tank was inspected, the scope was revised to include additional repairs needed to bring the tanks into compliance.
Repair work completed under the Task Order includes:
- Tank bottom replacement
- Cathodic Protection installation
- Installation of flexible membrane liners for secondary containment
- Installation of high/low level alarms
- Tank coatings and linings
Related Projects
Related News
“Fueling a Worldwide Mission” Article Featured in The Military Engineering Magazine
Project Manager John Malutich’s article “Fueling a Worldwide Mission” was featured in the November | December issue of The Military Engineer (TME) magazine. The article discusses a new state-of-the-art fueling station designed and constructed by Pond at Moody Air...
Pond Hires John Lathram, PMP, API as Program Manager
Pond is pleased to announce the hiring of John Lathram as program manager for the Oil and Gas division’s fuel construction sector. Based at Pond’s corporate office, he brings with him more than 30 years of exceptional experience in environmental remediation, fuel...
Strengthening Japan’s Fishing Economy through Fueling Engineering
With 32 military bases in Okinawa, Japan, and the need for fuel for military ships and aircraft, the U.S. Defense Logistics Agency (DLA), Government of Japan (GOJ) and Pond are working together to provide a solution that will save costs, time, allow larger ships to...