Atlanta Gas Light (AGL) | Northeast Georgia Expansion (NGX) 24″ Transmission Line - Marietta, GA
This project consists of approximately 10-miles of 24” steel transmission pipeline with a planned MAOP of 1200-psig. Pond provided engineering design, survey, SUE, cathodic protection design, environmental services and land acquisition services as well as construction administration and support services. This project included two mainline valve stations with remote monitoring and wireless communication, the demolition and tie-in to existing facilities as well as multiple directional drill designs. In addition to engineering and AC Mitigation design in-house, Pond managed subcontractors including topographic and SUE survey, environmental services, land acquisition, geotechnical analysis, landscaping repair estimates and analysis and septic system evaluation.
KEY ELEMENTS:
This project involves coordination with existing high pressure lines to address tie-ins and protection of existing systems during construction. Numerous installation methods were evaluated throughout the project to determine the one best suited for each roadway, stream or wetland crossing within the narrow construction corridor.
Installation of approximately 10 miles of 24” diameter high pressure pipeline.
This project passes through a heavily developed area with significant landowner, utility and constructability challenges driving multiple unexpected design changes through the design cycle of the project.
Related Projects
Related News
Pond Ingenuity Fall 2017 edition now available
Pond’s employees show amazing ingenuity in providing solutions to our clients every day, which is highlighted in Pond Ingenuity, a magazine about our staff and all the innovative, progressive projects and ideas they produce. To keep our clients in the loop of the...
Pond’s Integrity and Corrosion Management Department Performs Corrosion Evaluation
Pond’s Integrity and Corrosion Management team recently performed a corrosion evaluation on coal silos for a client. Led by Senior Project Manager David Hunter and Technical Director Sasan Hosein, the team went onsite to investigate and form a solution for extending...
Pond hires Benjamin Entrekin, PE CFPS to lead new compliance program for Energy division
Pond is pleased to announce its hiring of Benjamin Entrekin as senior fire protection engineer for the Energy division. With more than 20 years of consulting experience in the fuel, aviation, midstream, energy, water and wastewater spaces, for both the government and...