TECO Peoples Gas (TECO) is evaluating the installation of a 16” pipeline connection between two existing natural gas transmission lines to improve operational flexibility and system resiliency. This new pipeline will commence near the intersection of Heckscher Drive and Eastport Road, and terminate near the intersection of Main Street and Pecan Park Road. TECO has requested Pond to conduct a formal study to evaluate route alternatives between these tie-in locations and develop a numerical ranking for each route alternative. The study will also consider the means and alternatives to minimize landowner impact and risk and will include elements required for potential property condemnation.

Key Elements: 
Develop preliminary route alternatives based on desktop evaluation. Evaluation of existing parcel lines, major environmental features, and major constructability concerns.
Review preliminary route alternatives with TECO project team. Consider TECO’s strategic objectives and growth in the area.
Field evaluation of route alternatives. Pond’s project team, including engineering, environmental, and a construction contractor representative, will visit the route alternatives to evaluate constructability, environmental challenges, safety, and engineering considerations.
Detailed analysis, report preparation, and mapping preparation. Pond will incorporate field evaluation and additional detailed desktop study information into a comprehensive report document with mapping appendices.
Detailed cost estimate (+/- 25%) development.

Related Projects

Related News

Despite Coronavirus, Essential Work Continues to Keep Our Nation Safe

Despite Coronavirus, Essential Work Continues to Keep Our Nation Safe

As the Coronavirus continues to upend most aspects of our daily lives, organizations are constantly searching how to navigate these disruptions. For most, daily operations were limited to remote work and online conferencing, but the task of powering our nation’s vital...

Pond Featured in PaintSquare Press

Pond Featured in PaintSquare Press

Coatings Program Manager David Hunter discusses the Undeniable Value of Coatings Condition Surveys in the Summer edition of PaintSquare Press. His article (located on pages 8-11) explores the dangers of forgoing thorough, quality control procedures. He provides case...

Pond’s Energy Team Expands Client Service in the Northeast Region

Pond’s Energy Team Expands Client Service in the Northeast Region

ATLANTA - (5.06.2020) - Pond is expanding our Energy client service to the Northeast region. With the addition of Philadelphia-based expertise, the firm is extending the reach of our efficient energy solutions with professionals who have a strong industry presence and...

Pin It on Pinterest