Newnan Bypass Pipeline - Coweta County, GA

Pond provided engineering design work on the Newnan Bypass, consisting of approximately 17.4 miles of 16” steel transmission pipeline with a planned MAOP of 1200 psig. Thus far, Pond has provided a detailed Cost/Resource loaded schedule to exceed AGL’s timeframe for the “Gas On” period. Pond has also completed the initial concept design and P&ID for the Regulator Station; completed the concept design to minimize survey time and identify problem areas from an environmental and construction standpoint; and implemented a program to aid in land management and acquisition.